Featured

Feature Project
Water Facilities Master Plan Update

Eastern Municipal Water District

Relevant Project features:

  • Updated hydraulic model to incorporate updates from the District’s GIS
  • Validated model by comparing pressure zone operations with operational (SCADA) data for peak week 2013 and 2014 conditions
  • Performed hydraulic evaluations to identify system deficiencies and recommended improvements, and developing an optimized capital improvement program, identifying costs and time line for implementation
  • Evaluated the water system under both average and peak demand conditions. 

More project information here