West Yost was recently selected to provide construction
management services for the City of Modesto’s $100 million Phase
2 Biological Nitrogen Removal/Tertiary Treatment Project. West
Yost has completed the constructability review of contract
documents. Phase 2 work will include construction of a new
advanced secondary treatment and tertiary treatment facilities
within the footprint of the existing secondary plant.
Mountain House’s Wastewater Treatment Plant was built in three
phases and completed by means of a design-build project
delivery method. West Yost provided full-time, onsite
construction management services for all three phases of the
project, which consisted of a new and subsequently
expanded WWTP, civil/site work, roadways, utilities, and
appurtenant facilities.